Project:   Rans - S-21 Outbound   -   VIEW REPORTS
Total Hours:2341.9
Start/Last Date:Mar 06, 2018 - No Finish Date
 
Friendly URL: https://eaabuilderslog.org?s=Voltar-S21

Home or Last Project Picture

Apr 25, 2024     ELT Antenna - (3.5 hours)       Category: Avionics
Groomed ELT wiring and fabricated a 0.032” 2024-T3 doubler for ELT antenna that stiffens the skin. The doubler has joggled edges to fit over the bulkhead and former/longeron and be riveted in place to the existing structure. I will also use a 2” diameter 0.040 round disc under the antenna. Primed doubler with Super-K. The purpose of the doubler is to minimize skin buckling and relieve stresses on the bulkhead/longeron rivets. I may also add rivets for additional strength.

Also, rough trimmed rudder cable fairings. Starting to complete small jobs in preparation for canopy work.


 